Application for building permit done

May 12, 2016
by

Having waited 30 days for possible complaints on the positive decision of our exemption permission for the position of the workshop we have now filed the official building permit.

The scope of the permit application includes this time:

  • the actual building permit application
  • the building position plan according to the zoning

Asemakaava_PermitApplication

  • the floor plan
  • the building facade drawings from all directions
  • the exemption permission approved by the municipality a month ago

We’ll see how long the permit process takes this time. When we built the Villa we were positively surprised about the fast turnaround of the application. Maybe, we get lucky and have already a decision before the summer vacation and can do the site inspection for the permit during our vacation.

Advertisements
No comments yet

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: